Project: Skaneateles Falls – Stauffer Chemical
Major Project Tasks:
- Remediation of the former Stauffer Chemical Plant in Skaneateles Falls, NY
- Excavation, characterization and disposal of over 400,000 tons of contaminated materials
- Demolition and disposal of a former chemical plant
- Temporary relocation of creek running through the property
- Installation of steel sheet piling
- Underpinning of 20’ concrete retaining wall
- Design and construction of an extensive series of dewatering pumps and transmission lines to by-pass the flow of an active creek channel for four months (system capacity 45,000 gpm)
- Riverbank excavation and restoration
- Reconfiguration and O&M of onsite water treatment facility
Major Project Contaminants:
- VOCs
- SVOCs
- PCBs
- Heavy Metals
- PAHs
Significant Project Obstacles:
- Active stream bypass to facilitate sediment excavation and restoration
- 24/7 mass dewatering needs in major excavation areas
- Staging and characterization of multiple waste streams associated with over 400,000 tons of impacted soils
Location: Skaneateles Falls, NY
Owner: Stauffer Management
Engineer:SPEC Consulting LLC
Project total: $12,000,000 |