Tonawanda, NY: Rehab of containment berms for tank farm

Constructed access roads and HDPE overflow pipes.

Placed and compacted 10,000 cu yd of clay to re-grade existing dikes. Constructed over a mile of drainage trench. Regraded 12,500 sq ft of inner dike wall, installed 65,000 sq ft of Claymax Bentomat™ liner; placed stone to ballast liner.

Location: Tonawanda, NY
Owner: NOCO Energy
Engineer: SPEC Consulting
Project total: $500,000

 
 